We successfully carried out what seemed like the impossible to clear vegetation and trees within a 13.5km strip to accommodate a new South West Water pipe line in just five weeks! Our clients (May Gurney) were delighted with not only our rapid progress but also the very high standard of work throughout. Within the pipe line trace large trees were sectionally dismantled, vegetation was cut down and the fire wood and woodchips were moved to the landowners stockpiles for reuse. Over 100 hedges had the growth reduced to below a 300mm height to prevent nesting birds becoming present and then the hedges were fenced to ensure they were stock proof before the pipe line main contract began.
WH Bond & Sons Ltd Trerule Farm, Trerulefoot, Saltash, Cornwall, PL12 5BL.